Concrete Patio Slab: A Complete Worked Estimate
A complete concrete estimate for a 12 by 10 foot patio slab 4 inches thick, with bag counts and a ready-mix comparison.
A patio slab is the heaviest project in this series, and the one where an estimating error hurts most, because concrete cannot be paused while more material is fetched. Once mixing starts, the slab has to be finished in one continuous operation. The estimate below works a single modest patio all the way from its footprint to three alternative bag counts, and then considers honestly whether bags are even the right way to supply it.
The slab being cast
The patio measures 12 ft by 10 ft, which is 3.66 m by 3.05 m, giving a footprint of 120 sq ft (11.15 sq m). It sits against the house at ground level, intended for a table, chairs, and foot traffic rather than vehicles. The thickness throughout is 4 in, or 10.2 cm — a standard depth for a domestic patio on a properly compacted sub-base, deep enough to be durable without wasting material on strength the use does not require.
The slab will be formed with timber edges, laid over compacted hardcore, and finished with a slight fall away from the house so rainwater drains off the surface instead of pooling against the wall.
Step one: calculate the volume
First find the footprint:
12 ft × 10 ft = 120 sq ft (11.15 sq m)
Convert the thickness to feet so the units agree:
4 in ÷ 12 = 0.333 ft
Multiply footprint by thickness:
120 sq ft × 0.333 ft = 40 cu ft of concrete
Now express that volume in the other units suppliers and calculators use:
40 cu ft ÷ 27 = 1.48 yd³
In metric, the same slab is 1.13 m³ — check it directly: 3.66 m × 3.05 m × 0.102 m comes to roughly 1.13 cu m, confirming the imperial chain.
That 40 cu ft (1.48 yd³, 1.13 m³) figure already has a 10 percent waste allowance reflected in the bag counts that follow. Waste in slab work is real: some concrete stays in the mixer and barrow, the sub-base is never perfectly level so parts of the slab run slightly thicker, and spillage is inevitable across a pour of this size.
Run slabs of other dimensions through the Concrete Calculator and watch how quickly thickness changes the total — doubling depth doubles volume, while the footprint stays the same.
Step two: bag counts, three ways
Bagged dry mix is sold by weight, and each bag size yields a different volume of placed concrete. For this slab, with the 10 percent waste allowance included, the verified counts are:
- 74 bags of 80 lb (36.3 kg bags)
- 98 bags of 60 lb (27.2 kg bags)
- 147 bags of 40 lb (18.1 kg bags)
Read those numbers as a workload statement, not just a shopping figure. Seventy-four large bags is the fewest lifts, but each lift is the heaviest, and every bag must be emptied, mixed with water, barrowed, placed, and levelled before the batch stiffens. The 40 lb option nearly doubles the number of bags to handle at 147, in exchange for each one being far more manageable for a smaller team. The 60 lb count of 98 sits between the two on both measures.
Whichever size is chosen, the total concrete placed is the same 40 cu ft (1.48 yd³, 1.13 m³). Bag size changes the labour pattern, never the volume.
Full shopping list
| Item | Quantity needed | Buy |
|---|---|---|
| Concrete mix, option A | To place 40 cu ft (1.13 m³) including 10% waste | 74 × 80 lb bags |
| Concrete mix, option B | Same volume, smaller bags | 98 × 60 lb bags |
| Concrete mix, option C | Same volume, lightest bags | 147 × 40 lb bags |
| Sub-base hardcore | To form a compacted layer under a 120 sq ft (11.15 sq m) slab | Enough to cover 120 sq ft |
| Formwork timber | Around the perimeter, 12 + 10 + 12 + 10 = 44 ft (13.41 m) | Lengths totalling at least 44 ft |
| Formwork stakes | To hold the timber line along 44 ft of perimeter | 1 pack |
| Damp-proof membrane | To cover 120 sq ft (11.15 sq m) under the slab | A sheet at least 12 × 10 ft |
| Reinforcement mesh, optional | To cover the 120 sq ft slab area if specified | 1 sheet cut to size |
| Release or curing compound, or polythene | To cover 120 sq ft while the slab cures | Enough to cover the full slab |
Bags or ready-mix for this slab?
At 1.48 yd³ (1.13 m³), this patio sits in the awkward middle ground of concrete supply, and the right answer depends on crew and access rather than on the volume alone.
Bags offer total scheduling control. The material waits in a dry stack until the day is right, work can proceed at the team’s pace in sections divided by formwork, and there is no vehicle to receive. The cost of that control is physical: mixing the equivalent of 40 cu ft (1.13 m³) bag by bag is a long, heavy day, the concrete goes down in many small batches whose consistency varies, and the risk of cold joints between batches has to be managed by planning the pour sequence carefully.
Ready-mix inverts every one of those trade-offs. The whole volume arrives uniform and can be placed in a fraction of the time, which produces a more consistent slab. In exchange, the site must be completely ready when the truck arrives, access for the vehicle or a pump must exist, enough hands must be present to place and finish 1.48 yd³ before it stiffens, and any delay in the formwork or weather becomes urgent rather than merely inconvenient. Part-loads of this size may also be awkward to arrange, which is a practical question to settle with a supplier before committing to that route.
For a 12 by 10 ft (3.66 by 3.05 m) patio with good access and several helpers, ready-mix is usually the calmer day. For a rear garden reached only through the house, or a team of two working steadily, the 74 × 80 lb or 98 × 60 lb bag route, split across formed sections, is often the realistic one.
How bag yield is derived from volume is explained in concrete bag yield explained.
Order of work
Excavate the patio area, compact the ground, and spread and compact the sub-base. Build the formwork to the 44 ft (13.41 m) perimeter, set its top edge to the finished slab level with a gentle fall away from the house, and stake it firmly enough to resist the pressure of wet concrete. Lay the membrane, and mesh if it is being used, inside the forms.
On pour day, work from the far corner back toward your exit point, placing, spreading, and tamping the concrete in strips, then screed it level with the form tops. Finish the surface once bleed water has disappeared, cut or form joints as planned, and cover the slab to cure slowly. Keep foot traffic off it until it has hardened properly, and leave the formwork in place until the edges can support themselves.
Mistakes specific to this project
Under-ordering is the catastrophic error, because a slab cannot be topped up tomorrow with a seamless result. The 10 percent allowance inside the counts of 74, 98, and 147 bags is not generosity — it is the margin that guarantees the pour finishes. Do not trim it away to make the shopping list look leaner.
Adding too much water at the mixer is the second serious fault. A sloppy mix is easier to place in the moment and weaker forever afterwards, with a surface prone to dusting and cracking. Measure the water for each batch instead of judging it by eye when tiredness sets in late in the pour.
A third mistake is casting right up against the house with no fall. A level or inward-sloping 120 sq ft (11.15 sq m) surface collects every rainstorm and delivers it to the wall. Build the drainage slope into the formwork before any concrete arrives; it cannot be added afterwards.
Finally, do not strip the forms or load the slab early out of impatience to use the patio. The surface may feel hard while the slab is still gaining the strength that keeps its corners intact. Respect the curing period, keep the slab covered and damp as directed, and let the last stage of the project be patience.
Next step: set your own patio's dimensions and thickness in the Concrete Calculator, compare its bag count against a ready-mix minimum order, and make the call with the pour-day plan in this estimate open beside you.